<aside> 📅
13 October 2026 update: James confirms the homepage preview is good. The current working go-live target is 12 November 2026, subject to a validated delivery and QA schedule. CareChoice aims to provide consolidated design feedback on 14 October; Ven plans to return the first revision within 24 hours of receiving complete feedback. End-user testing follows that revision and may take about a week. 21 October second review and 23 October final design approval are proposed checkpoints, not confirmed deadlines. The September dates and 6 November launch target in the snapshot below are superseded. See the dated ‣ and its approval gates.
</aside>
<aside> 📍
Where we are: Design stage. Your final review of the homepage design (Round 3) is the last step before the remaining pages move ahead. Updated 28 September 2026.
</aside>
| Stage | Status | Timing |
|---|---|---|
| Discovery and site structure | ✅ Complete | 19 Aug |
| Homepage design | 🔄 Final review with you (Round 3) | Sign-off by 29 Sep |
| Remaining page designs and builds | ⏳ Next | 7 – 26 Oct |
| Full design approval | ⏳ Upcoming | 16 Oct |
| Staging site review and user testing | ⏳ Upcoming | 27 Oct |
| Pre-launch readiness check-in | ⏳ Upcoming | 28 Oct |
| Launch | ⏳ Upcoming | Target Fri 6 Nov, confirmed after homepage sign-off |
| Post-launch review and 30-day defect period | ⏳ Upcoming | About 2 weeks after launch |